History

|
2000-2001 |
Commissioning of the Hazira-Mora pipeline, our first pipeline. The section was 14 kms long. |
|
2001-2002 |
Commissioning of 45 kms of the Amboli-Dahej pipeline and the total network length increased to 59 kms. |
|
2002-2003 |
Commissioning of 66 kms of gas pipeline, which included Mora-Utran, Cairn-Mora and Bhadhut-Paguthan pipelines, and GNFC, Videocon and Mora Kribhco spur lines. The total network length increased to 125 kms. |
|
2003-2004 |
Commissioning of the Paguthan-Baroda pipeline. The total network length increased to 209 kms. |
| 2004-2005 | Commissioning of the Baroda-Ahmedabad-Kalol pipeline, the GACL-Petronet pipeline, the Mora-Sajod pipeline and the Kalol-Santej pipeline, extending the network by an additional 224 kms. The total grid length increased to 433 kms. Completion of construction of the Gandhinagar spur line, which was 15 kms in length. The total grid length increased to 448 kms. The Company, GSPC and IDF executed the Share Subscription and Shareholders Agreement, pursuant to which IDF agreed to subscribe for equity shares in the Company in an amount of Rs.900 million. The company demonstrated the reverse flow capability for the gas network. |
| 2005-2006 | Mora gas terminal terminal is commissioned. The
EPC and engineering contracts for Mora-Vapi, Anand-Rajkot,
Kalol-Himmatnagar, Kalol - Mehasana and Aanklav-Dhuvaran pipelines
are awarded and under execution. |
| 2006-2007 | Commissioning of Mora Vapi, Anand Rajkot Pipeline Project, Kalol Mehsana Pipeline Project, Kalol Himmatnagar Pipeline Project. |
|